SUBIACO, January 22, 2019 - Gold developer West African Resources Ltd. (ASX, TSXV: WAF) is pleased to report progress on its Sanbrado Gold Project ("Sanbrado"), Burkina Faso, for the quarter ending 31 December 2018.
Highlights
Project Development Summary
Underground mining contract awarded to Byrnecut
Mill package awarded to Outotec, order placed for 4MW SAG and ball mills
EPCM contract for Sanbrado awarded to Lycopodium
Earthworks, camp and box cut for underground access commenced by WAF construction team
Further Key hires completed for construction, operations and security teams
M1 South Diamond Drilling
1km diamond hole intercepted extensive visible gold returning 25m at 15.03 g/t Au
Intercept located 220m vertical beneath existing Probable Ore Reserves, confirms potential to extend M1 South underground mine life past 4.5 years
Parallel high-grade zone at M1 South intercepted 300m below surface, 180m east of main zone 2m at 138.4 g/t Au and 5.5m at 15.5 g/t Au
Infill drilling returns 21.5m at 15.3 g/t and 14.5m at 19.9 g/t Au
Corporate Summary
West African fully funded through to gold production in 2020 at Sanbrado
US$200 million finance facility secured with Taurus Funds Management Pty Ltd
Fully underwritten institutional Share Placement completed raising A$43.2 million
Share Purchase Plan offer for up to A$5 million enabling retail shareholders to participate in Sanbrado project funding closes January 25, 2019
Updated security protocols and procedures for staff and contractors in Burkina Faso
December 2018 Quarter Summary
5,656m drilled
A$7.8m exploration and mine development expenditure
A$4.2m administration costs (including costs associated with project finance raising - debt and equity)
A$66.4m cash at bank at 31 December 2018
March 2019 Quarter Plans
Completion of feasibility study optimisation and update
Exploration drilling near surface targets in trucking distance to Sanbrado
Award of open pit mining contract
Completion of stage 1 camp (120 rooms), admin building, clinic and temporary power station
Major mechanical and electrical equipment procurement
Structural steel and platework fabrication commencement
Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!